Core Scientific announced it has received conditional approvals from the Electric Reliability Council of Texas (ERCOT) for over 1.4 gigawatts (GW) of existing and planned power capacity across its three data center sites in Texas. The update clarifies the power status for its operations and major expansion projects within the state's regulatory framework.

Key Details

  • Denton Site (371 MW): The existing 297 MW is approved as "longstanding existing load" and an additional 74 MW for expansion are both not subject to the Batch Zero allocation process.
  • Pecos Site (600 MW): The existing 300 MW and an additional 300 MW have been conditionally approved in ERCOT's Batch Zero process, with final allocation pending the process conclusion.
  • Hunt Site (431 MW): The planned 431 MW has been conditionally approved in Batch Zero as an "Advancing Large Load," with interconnection studies completed, collateral posted, and construction commenced.