The U.S. Department of Energy (DOE) issued an emergency order effective August 23, 2026, compelling PJM Interconnection and Constellation Energy to maintain operations at Pennsylvania's Eddystone Generating Station. This mandate keeps two generating units online to bolster Mid-Atlantic grid reliability during recurring heatwaves and peak air conditioning demand.

The order overrides planned retirements through November 20, 2026, ensuring the units remain available for dispatch to prevent potential blackouts. The DOE explicitly cited the necessity of natural gas, coal, and nuclear power for grid stability during periods when renewable energy sources may be less reliable.

This government intervention creates a direct tailwind for natural gas demand within the largest U.S. power market. By forcing generation capacity to remain active, the order guarantees fuel consumption that would have otherwise ceased, providing price support for regional natural gas.